City of Tampa Response to the SoHo Business Alliance’s Alternate Route

City of Tampa’s Response to the SoHo Business Alliance’s Alternate Route

The City has spent 18 months studying nearly two dozen alternatives. The design team engineers have invested countless hours in identifying the best solution to address flooding in Parkland Estates and Palma Ceia Pines.

When this new proposal was presented last week, even at this late stage in the process, we asked our design team to evaluate it immediately.

The engineering review is clear: this alternative does not remove enough stormwater to meet the project’s flood-relief goals. It would also require a longer route, a larger construction footprint, and cost more.

We have a responsibility to recommend a solution that we know will work. After extensive study and engineering, we have found only one solution that can remove the volume of water that we’re dealing with.

Here are the City’s concerns with this alternate route.

  • Does not achieve the project’s flood-relief goals: The proposed storage vaults do not have enough capacity to manage the volume of stormwater generated during a 5-year/8-hour storm without significant additional upgrades to the existing drainage system. As proposed, significant roadway flooding would remain.
  • Longer route means more construction: The alternative route is approximately 35% longer than the South Howard route, increasing both construction costs and the time needed to complete the project.
  • Would significantly impact the existing tree canopy: Construction along the alternative route could require removal of a significant number of Grand Oaks and other mature trees, changing the character of affected neighborhoods.
  • Could increase flooding in Palma Ceia without additional improvements: Unless the existing drainage system is upgraded all the way to Hillsborough Bay, the alternative could increase flooding in the Palma Ceia neighborhood.
  • Could require acquisition of private homes or property: Upgrading the drainage system beneath the CSX railroad and Selmon Expressway could require acquisition of one or more homes or properties adjacent to the railroad in Palma Ceia.
  • Eliminates existing stormwater treatment: The AMI pond currently provides permitted water-quality treatment for approximately 60 acres of the watershed. Construction of the proposed vault would eliminate that treatment, with no replacement identified in the alternative plan.
  • Relies on pumps rather than gravity: The proposed vaults would depend on pumps to move stored water out of the system. Unlike a gravity-based system, pumps introduce the risk of mechanical failure during severe storms and hurricanes and require ongoing operations and maintenance. These large pumps and backup generators would need to be housed in a permanent structure not shown in the proposed plan, creating a large, highly visible structure with significant noise and potential disruption to the surrounding neighborhood.
  • Creates significant railroad construction challenges: CSX has a strict right-of-way (R/W) policy that prevents construction within its R/W or near the railroad. This route appears to have 800 linear feet of the existing system that will need to be upgraded that lies within CSX R/W and very close to the railroad.
  • Crosses private property: The proposed connection between the AMI pond and Parkland Estates crosses a privately owned parking lot and other private property.
  • Would require reconstruction of the AMI parking deck: Installing the proposed underground vaults would require demolition and reconstruction of the 2+ acre privately owned AMI parking deck, necessitating HCA approval, temporary parking loss, and additional reconstruction costs.
  • Requires a massive underground storage vault: The alternative calls for storing approximately 15 million gallons of stormwater underground, which would require extensive excavation and a large, complex, and costly structure.

Notice to Residents/Businesses – January 26, 2026


The City of Tampa would like to share upcoming opportunities for public input on the South Howard Flood Relief Project. Planned infrastructure improvements will be discussed during a Tampa City Council workshop in the morning, followed by a Tampa City Council meeting in the evening on Thursday, January 29, 2026.  
At the evening city council meeting, council members will vote on whether to transfer $21,495,000 within the Stormwater Bond Series 2023 Fund for the South Howard Flood Relief Project.  

Your voice matters in this process. City Council relies on feedback from residents and neighborhood leaders to better understand local needs and concerns, helping shape informed decisions that reflect the community’s perspective. We encourage the community to participate by attending the workshop and the council meeting in person or by submitting comments in advance via email to the Tampa City Council. Community input is a vital part of City decision-making, and your participation helps ensure Council members have a clear picture of neighborhood priorities and the level of support for the project.  

If you have any questions about the workshop, project details, or how to submit comments, please get in touch with the South Howard Flood Relief Project team at (813) 467-7887 or info@SHStormwater.com. 
 

Notice to Residents/Businesses – December 5, 2025

Beginning Friday, December 5, 2025, through Friday, December 12, 2025, field technicians, with ECHO UES, Inc., will be performing survey work as part of the South Howard Flood Relief project design. The survey work will include reviewing the right-of-way boundaries within the South Howard project area. These activities will take place Monday through Friday, between the hours of 7 a.m. and 7 p.m.