Construction Phases

The work will be phased, with crews working on smaller segments at a time and restoring each area as they move up Howard and into Palma Ceia Pines. Work will be limited to sections of about 400–600 feet at a time, reducing how much of the corridor is under active construction.

Phases
24

Estimated construction durations. Subject to change.

Map of the 24 construction phases along S. Howard Avenue, W. Swann Avenue, S. Audubon Avenue, W. Parkland Boulevard, W. Fountain Boulevard and W. Bristol Avenue. Every phase is also listed beside the map.12A2B3456789101112131415161718192021222324
  • Under construction
  • Complete
  • Upcoming

Choose a phase on the map or in the list to view its location and estimated duration. Once construction begins, the active phase will be highlighted in amber.

All 24 phases

In construction order, from the outfall on Hillsborough Bay north.

Phase limits are approximate, traced from the City’s 60% design phasing board, and subject to change. Map data © OpenStreetMap contributors.