Draft Preliminary Engineering Report Appendices (18)

August 11th – 60% Design Open House

March 5th – 30% Design Open House

August 2026 draft

Project Map – Stormwater Improvements

This map was on the Project Information page. The construction phase map replaces it.

Download the map (PDF)Construction phase map

South Howard Flood Relief Project location map: the proposed Phase 1 box culvert runs up S. Howard Avenue from the existing triple box outfall on Bayshore Boulevard to W. Swann Avenue and west to S. Audubon Avenue, with Phase 1 secondary storm sewers in Parkland Estates and along W. Bristol Avenue, future-phase storm sewers into Palma Ceia Pines and New Suburb Beautiful, and the AMI, Zom, Swann and Albany ponds.

November 2025

Project Schedule

This schedule was on the Project Information page. It showed project design running from January 2025 to March 2026; the note beneath it read: “Activities and schedules are subject to weather and other unforeseen circumstances. Project construction is anticipated to begin in late summer 2026.”

Project schedule, November 2025: a single Project Design bar from January 2025 through March 2026.

As of November 2025

Current/Upcoming Activities

All survey work for the project’s design phase is complete. Additional surveying may be performed if engineers identify information needed to finalize the design.

Right-of-way line verification is currently underway and expected to be completed by mid-November 2025.

Geotechnical boring (drilling of small test holes in the ground to explore sub-surface conditions) began on W. Swann Avenue on Saturday, November 1, 2025, and will continue into the Parkland Estates neighborhood. This work is necessary because future stormwater pipes will extend into Parkland Estates to move water to the planned box culvert on W. Swann Avenue.

The City has received questions about survey activities along W. Bristol Avenue, west of S. Howard Avenue. A Sunshine 811 utility location request mistakenly included a larger area of W. Bristol Avenue than intended. Work along W. Bristol Avenue is only expected between S. Howard Avenue and the Selmon Expressway to support drainage for the Selmon Expansion project. The recommended box-culvert route under design is the W. Swann Avenue route.

The information gathered helps ensure plans are accurate and construction is designed safely and effectively.

Box culvert construction will require City Council approval once the project reaches the 60% design milestone. Those drawings, along with the proposed Guaranteed Maximum Price (GMP) contract, are expected to be presented to the City Council in summer 2026.